A final decision on federal funding for the Blue Line Extension could still be more than a year away, but a leading member of Congress from Minnesota is stepping up his calls to kill the controversial light rail project before construction ever begins.
U.S. Rep. Tom Emmer, R-Minn., now predicts the Federal Transit Administration (FTA) will decline to cover more than $1 billion of the Blue Line Extension’s projected $3.2 billion price tag.
“They’re going to put the dollars, the limited dollars that the federal government has, to the best use possible,” Emmer told 5 INVESTIGATES. “That is not trains.”
Emmer’s bold prediction comes as the FTA just signed off on an environmental review for the Blue Line Extension, which unlocked millions of dollars to support businesses and community organizations serving people along the proposed route from Minneapolis to Brooklyn Park.
“It is a generational investment in communities where many people rely on transit to get where they need to go every day,” said Hennepin County Board Chair Irene Fernando in a recent statement.
2 down, 1 to go
The FTA has not responded to requests for comment about Emmer’s prediction that the agency will cut off federal tax dollars for the Blue Line project, but the Congressman has already counted victories with two other commuter rail lines that he targeted as “financially irresponsible.”
In May, Emmer and three other House Republicans from Minnesota wrote to the Transportation, Housing, and Urban Development Subcommittee asking it to stop federal funding for three projects.
Two of them, the Northstar Commuter Rail and the Northern Lights Express, are now essentially dead.
The Blue Line Extension is the last project remaining on Emmer’s list.
“We’re talking about a total cost of $3.2 billion for 13 miles of rail. The math doesn’t work,” Emmer said. “If you’re going to invest that whole $3.2 billion, you might as well just buy all the riders that are going to use that thing a new car.”
Cost in perspective
Project managers with Hennepin County offer a vastly different perspective on the light rail project, which has been in various stages of planning for a decade.
They point out that the Blue Line Extension’s estimated cost per mile of $261 million is lower than comparable light rail projects across the country.
The West Seattle Link Extension in Washington and the Southeast Gateway Line in Los Angeles are projected to cost around $600 million per mile.
Austin Light Rail Phase 1 in Texas, also known as Project Connect, is now expected to cost more than $830 million per mile.
Fernando says she believes in the Blue Line Extension project now more than ever.
“I have had the opportunity to work on this project since 2019,” Fernando said during an interview with 5 INVESTIGATES in July. “I feel very confident with the path that we have outlined.”
But when pressed for an answer about the prospect of losing federal funding and whether Hennepin County could build the new line without financial help from the FTA, she was less decisive.
“I can’t speak in hypotheticals that far out,” Fernando said. “We are moving forward to this project full steam ahead on behalf of our residents.”